Breakdown of Irrelevant Items Added to the Contract of Govt High School Ilorin
Click Irrelevant items in GHS Contract BoQ to download the breakdown of irrelevant items added to the Bill of Quantity (BoQ) of Government High School Ilorin worth over 40 million naira.
The irrelevant items are in the following categories:
1. Supervision, Monitoring and Evaluation (₦4,081,590.36)
2. Project Design and Production of BoQ (₦1,723,368.66)
3. Progress Photographs (₦428,071.80)
4. Project Labelling (₦735,000)
5. Contract Administration (₦125,000)
6. Project Vetting (₦5,580,000)
7. 3% Development Levy and 5% Withholding Tax (₦25,418,159.56)
8. Repetition of General Contingency, Preliminary, and Monitoring and Evaluation at the end of the BoQ Summary (₦2,749,165)
Total amount for irrelevant items = ₦40,840,355.38